The Library’s exterior has been in transformation since January 2026 as all the windows in the building are being replaced with new windows.  Assistant Vice President for Campus Planning and Facilities Charlotte Diehl, AIA, observes that the new windows will include the following benefits:

  • Improved thermal performance
  • Improved air sealing
  • Bird proof glass
  • Ease of operation to comply with ADA requirements (e.g., some of the windows can open)

Leonard Lief Library is a brutalist style building with primary building materials of concrete and glass.  It contains many windows around its circumference, so much labor is required on each floor during replacement process.  Library Renovation team members made the decision to close the 2nd and 3rd floors (except for Bloomberg Lab on 2nd floor) during period when windows on that floor are being replaced.

The project, managed by Fides Gardiner and Gerard Igboabuchi of Dormitory Authority of New York (DASNY) is organized in the following phases:

Phase 1: Furniture and Books Removal

Cleared library shelves positioned along windows, showing empty shelving units prepared for nearby construction work.
Library shelves near the windows emptied to prepare for window replacement

Phase 2: Protection and Architectural Removal 

Lehman Library windows being restored
Plastic enclosure installed to protect Library interior during window installation

Phase 3: Abatement and Demo 

Library Cubicles
Plastic enclosure sets the stage for abatement process, done after Library closing

Phase 4: Window Prep 

Lehman Library outside the building while windows are being replaced
Window openings covered with wood after old window is removed

Phase 5: Window Install

Third-floor windows are waiting to be installed
Windows on Library’s 3rd floor, waiting to be installed
Lehman Library New Windows
Row of new windows installed on Library’s 3rd floor
Workers outside of Lehman Library installing new windows.
Next set of 3rd floor windows installation in process
Lehman Library with Scaffolding
Installation continues

Last phase of the work on each floor is to return the books, architectural features, and furniture to their respective spaces and to clear the floor.  This project is expected to conclude at the end of July 2026.